ONTARIO 🧑🔎 ⚛️ 💵 Ontario Refurbishing Hydroelectric Stations in Niagara
Sunday, 05 May 2024 12:00.PM
- Stations would supply reliable, affordable and clean power for an additional 30 years -
The Ontario government is supporting Ontario Power Generation’s (OPG) plan to refurbish its hydroelectric stations in the Niagara region, including the Sir Adam Beck Complex at Niagara Falls. This $1 billion dollar infrastructure program would secure up to 1,700 megawatts (MW) of clean electricity, equivalent to powering 1.7 million homes, helping to meet increasing demand from electrification and fueling the province’s growth.
“For more than 100 years hydroelectric power from Niagara Falls has powered our province, and with today’s investment we’re extending the life of these stations by another 30 years to help Ontario meet its growing electricity needs,” said Todd Smith, Minister of Energy. “This refurbishment program – part of our Powering Ontario’s Growth Plan - will create jobs and ensure we have the power we need for the next major international investment, the new homes we are building and industries as they grow and electrify.”
OPG and its partner, GE Vernova, will refurbish up to 25 units in total at the Sir Adam Beck Complex as the first phase of this work beginning in 2025, increasing the stations capacity by up to 50 MW. OPG is also developing future plans for its DeCew I and DeCew II generating stations in the region.
“Upgrading and optimizing OPG’s renewable generation workhorses like the Sir Adam Beck complex is crucial to support the growing demands of electrification and a thriving economy,” said Ken Hartwick, OPG President and CEO. “Through this refurbishment, this hydropower facility will build on its century-plus history, and continue to produce the low-cost, reliable electricity Ontarians need for decades to come.”
The work at the Sir Adam Beck complex will take place over the next 15 years, creating more than 200 highly skilled and well-paid jobs in the Niagara region.
“Ontario is blessed with a diverse supply of clean energy sources. Through this historic investment in the Sir Adam Beck Generating Stations, we are able to keep costs down for families while funding more reliable sources of energy,” said Andrea Khanjin, Minister of the Environment, Conservation and Parks. “This investment will ensure a future of clean, reliable and affordable power in the province for generations to come.”
This investment in Ontario’s hydroelectric fleet is just one part of Powering Ontario’s Growth, the government’s pragmatic plan which outlines the actions the province is taking to meet growing energy demand and reduce emissions by expanding Ontario’s reliable, affordable and clean grid, including:
• Nuclear Energy – Advancing reliable, affordable and clean nuclear power through pre-development work at Bruce Power, four small modular reactors at Darlington and supporting OPG’s plan for refurbishing the Pickering Nuclear Generation Station.
• Competitive Procurements – Acquiring 4,000 MW of electricity generation and storage and launching more competitive procurements for non-emitting electricity resources including wind, solar, hydroelectric, batteries and biogas.
• New Transmission Infrastructure – Designating and prioritizing transmissions lines in Southwestern, Northeastern and Eastern Ontario that will power job creators including EV and EV battery manufacturing and clean steel production.
• Keeping Costs Down – Launching new energy efficiency programs on January 1, 2025, building on the government’s $342 million expansion of existing energy efficiency programs which are helping families and businesses reduce their electricity use so they can save money on their energy bills.
Quick Facts
• Ontario’s grid is one of the cleanest in the world with a diverse supply mix made up of nuclear, hydroelectric, renewables, natural gas and biomass.
• OPG operates four hydroelectric generation stations in the Niagara Region, Sir Adam Beck 1 and 2 and DeCew 1 and 2.
• The Sir Adam Beck facility has been a source of clean power for more than a century.
• The Sir Adam Beck facility produces about 12,300 gigawatt-hours of energy each year – about 35 per cent of OPG’s hydroelectric production, or about nine per cent of the electricity produced in Ontario.
"OPG’s investment at the Sir Adam Beck complex in Niagara Falls will ensure that Ontario has the power needed to support the growing demands of our economy, while creating 200 new, good-paying jobs for local workers. In addition, this refurbishment will help to provide the clean, green power we’ll need to fuel our province’s growing end-to-end electric vehicle and EV battery supply chain."
- Vic Fedeli
Minister of Economic Development, Job Creation and Trade
SOURCE: Ontario Ministry of Energy
-
Related materials:
- 18-Nov-2024 12:00 PM 🧑🔎 Youth Unemployment to Cost Canadian Economy $18.5 Billion by 2034, Warns New Report 💵
- 15-Nov-2024 02:33 PM 🧑🔎 Centennial College Amps Up Electric Vehicle Training 🚗
- 15-Nov-2024 12:05 AM 📬 CUPW Announces National Strike That Will Cause Delays for Canadians as Holiday Shopping Season Begins
- 14-Nov-2024 04:29 PM 🇨🇦🍁💵 Government Of Canada Announces Contracts for Recovery Vehicles to Support the Canadian Armed Forces
- 06-Nov-2024 12:00 PM 🇨🇦🍁💚💵Canada Releases Draft Regulations to Cap Pollution, Drive Innovation, and Create Jobs in the Oil and Gas Industry 🤔💭
- 05-Nov-2024 08:00 AM 💵🤔💭 A Candid Perspective About Career Transitions in the Financial Advisory Business
- 04-Nov-2024 02:28 PM 💵 Government Of Canada Invests in the Well-Being of Veterans and Their Families
- 04-Nov-2024 12:00 PM 🇨🇦🍁💵 Canada Brings International Leadership Ambition on Nature and Biodiversity to COP16 In Cali, Colombia 🌍🌄
- 18-Oct-2024 08:00 AM ONTARIO 👨🔬🔬 Ontario Science Centre’s Interactive Experiences Coming to CF Sherway Gardens and Harbourfront Centre this Fall
- 09-Oct-2024 06:51 PM 🇨🇦🍁💵 Governments Investing to Improve Ontario Farmland